Progress report · Wholesale Ordering Portal

Standing orders are live in your preview.

On trackUpdated

Forecast pace from the last 4 weeks

Done18 / 26pieces working in your preview
Pace3.3 / wkpieces released per week
Likely doneNov 2half of forecasts land on or before this date
Safe dateNov 12we are 85% confident of this date

Progress burn-up, pieces over time

0102030Sep 3Sep 17Oct 1Oct 15Oct 29Nov 12LikelySafeToday18Scope 22Scope 26
Burn-up chart data
DatePieces doneTotal scope
Sep 3022
Sep 10222
Sep 17522
Sep 24822
Sep 27924
Oct 11124
Oct 61326
Oct 81526
Oct 151826

The gap between the orange line and the grey line is the work left. When the grey line steps up, scope was added.

Milestones each one ends in a demo

  1. M1 · Sep 23Cafés can place ordersDone10 of 10 pieces done · 100%Demoed and live in production.
  2. M2 · Oct 14Standing orders and cut-offsDone8 of 8 pieces done · 100%Demo booked for Fri Oct 16.
  3. M3 · Oct 27Invoices and statementsIn progress0 of 5 pieces done · 0%2 of 5 pieces done.
  4. M4 · Nov 2Open to all café accounts0 of 3 pieces done · 0%Safe date Nov 12.

All pieces by value

18 done · 1 in progress · 1 up next · 6 planned

What the value numbers mean
  • 10 You asked for this directly
  • 9 Security, compliance or privacy requirement
  • 8 Makes something you asked for work (setup, admin screens, settings)
  • 7 High-value feature for your industry
  • 6 Improves something you asked for
  • 5 Standard in comparable products
  • 3–4 Foundation other features depend on
  • 1–2 Proposed idea, not yet approved
  • — Not yet rated
What the statuses mean
  • Done Finished and checked
  • In progress Being built now
  • Up next Starts next
  • Planned In the plan, not started

Select a piece to see what it does and what it builds on.

Showing 26 of 26

Planned pieces, their value and status
ValuePieceTrackStatusMilestone
10
Add to order and edit quantities#8 · M1
Value
10 of 10: You asked for this directly
Milestone
M1 · Cafés can place orders
Status
Done: finished and checked
Done
Sep 24
DoneM1
10
Reorder last week's order in one tap#15 · M2
Value
10 of 10: You asked for this directly
Milestone
M2 · Standing orders and cut-offs
Status
Done: finished and checked
Done
Oct 8
DoneM2
10
Weekly standing orders#16 · M2

A café sets up the order it wants every week once; the bakery receives it on the same day each week until the café changes or stops it.

Value
10 of 10: You asked for this directly
Milestone
M2 · Standing orders and cut-offs
Status
Done: finished and checked
Started
Oct 6
Done
Oct 12
DoneM2
10
Invoice PDF for each order#19 · M3

Every order gets a PDF invoice the café can download and the bakery can send by email.

Value
10 of 10: You asked for this directly
Milestone
M3 · Invoices and statements
Status
In progress: being built now
Started
Oct 13
In progressM3
9
Sign-in for bakery staff#5 · M1
Value
9 of 10: Security, compliance or privacy requirement
Milestone
M1 · Cafés can place orders
Status
Done: finished and checked
Done
Sep 17
DoneM1
9
Café accounts with their own sign-in#10 · M1
Value
9 of 10: Security, compliance or privacy requirement
Milestone
M1 · Cafés can place orders
Status
Done: finished and checked
Done
Sep 29
DoneM1
9
Open sign-up for every café account#25 · M4
Value
9 of 10: Security, compliance or privacy requirement
Milestone
M4 · Open to all café accounts
Status
Planned: in the plan, not started
PlannedM4
8
Product list import#3 · M1
Value
8 of 10: Makes something you asked for work (setup, admin screens, settings)
Milestone
M1 · Cafés can place orders
Status
Done: finished and checked
Done
Sep 11
DoneM1
8
Bakers' morning production sheet#22 · M4
Value
8 of 10: Makes something you asked for work (setup, admin screens, settings)
Milestone
M4 · Open to all café accounts
Status
Planned: in the plan, not started
PlannedM4
7
Delivery days calendar#4 · M1
Value
7 of 10: High-value feature for your industry
Milestone
M1 · Cafés can place orders
Status
Done: finished and checked
Done
Sep 14
DoneM1
7
New-order alert for the bakery team#6 · M1
Value
7 of 10: High-value feature for your industry
Milestone
M1 · Cafés can place orders
Status
Done: finished and checked
Done
Sep 19
DoneM1
7
Delivery zones on a map#11 · M2
Value
7 of 10: High-value feature for your industry
Milestone
M2 · Standing orders and cut-offs
Status
Done: finished and checked
Done
Oct 1
DoneM2
7
Café-specific price lists#13 · M2
Value
7 of 10: High-value feature for your industry
Milestone
M2 · Standing orders and cut-offs
Status
Done: finished and checked
Done
Oct 5
DoneM2
7
Cut-off time for each delivery zone#18 · M2

Each delivery zone has its own last time to order for the next morning; later orders move to the following delivery day.

Value
7 of 10: High-value feature for your industry
Milestone
M2 · Standing orders and cut-offs
Status
Done: finished and checked
Started
Oct 12
Done
Oct 15
DoneM2
7
Monthly statement per café#20 · M3

Once a month each café gets one statement listing its orders, invoices and payments.

Value
7 of 10: High-value feature for your industry
Milestone
M3 · Invoices and statements
Status
Up next: starts next
Up nextM3
6
Order history for each café#7 · M1
Value
6 of 10: Improves something you asked for
Milestone
M1 · Cafés can place orders
Status
Done: finished and checked
Done
Sep 22
DoneM1
6
Product catalogue with photos#9 · M1
Value
6 of 10: Improves something you asked for
Milestone
M1 · Cafés can place orders
Status
Done: finished and checked
Done
Sep 26
DoneM1
6
Minimum order per café#12 · M2
Value
6 of 10: Improves something you asked for
Milestone
M2 · Standing orders and cut-offs
Status
Done: finished and checked
Done
Oct 3
DoneM2
6
Order confirmation email to the café#14 · M2
Value
6 of 10: Improves something you asked for
Milestone
M2 · Standing orders and cut-offs
Status
Done: finished and checked
Done
Oct 7
DoneM2
6
Pause a standing order for a holiday#17 · M2

A café skips one or more weeks of its standing order, for a holiday or a closure, without cancelling it.

Value
6 of 10: Improves something you asked for
Milestone
M2 · Standing orders and cut-offs
Status
Done: finished and checked
Started
Oct 9
Done
Oct 13
DoneM2
6
Account page for café managers#21 · M3
Value
6 of 10: Improves something you asked for
Milestone
M3 · Invoices and statements
Status
Planned: in the plan, not started
PlannedM3
5
Bakery brand and colours#2 · M1
Value
5 of 10: Standard in comparable products
Milestone
M1 · Cafés can place orders
Status
Done: finished and checked
Done
Sep 9
DoneM1
5
Credit notes for returned items#23 · M3
Value
5 of 10: Standard in comparable products
Milestone
M3 · Invoices and statements
Status
Planned: in the plan, not started
PlannedM3
4
Project setup and private preview#1 · M1
Value
4 of 10: Foundation other features depend on
Milestone
M1 · Cafés can place orders
Status
Done: finished and checked
Done
Sep 8
DoneM1
2
Order by text message#26 · M4
Value
2 of 10: Proposed idea, not yet approved
Milestone
M4 · Open to all café accounts
Status
Planned: in the plan, not started
PlannedM4
—
Delivery driver notes#24 · M3
Value
Not yet rated
Milestone
M3 · Invoices and statements
Status
Planned: in the plan, not started
PlannedM3

What shipped latest 10

  • #18
    Cut-off time for each delivery zoneOct 15
  • #17
    Pause a standing order for a holidayOct 13
  • #16
    Weekly standing ordersOct 12
  • #15
    Reorder last week's order in one tapOct 8
  • #14
    Order confirmation email to the caféOct 7
  • #13
    Café-specific price listsOct 5
  • #12
    Minimum order per caféOct 3
  • #11
    Delivery zones on a mapOct 1
  • #10
    Café accounts with their own sign-inSep 29
  • #9
    Product catalogue with photosSep 26

Next up

  • #19
    Invoice PDF for each orderIn progress
  • #20
    Monthly statement per caféPlanned
  • #21
    Account page for café managersPlanned
  • #22
    Bakers' morning production sheetPlanned